Project: El Rancho Road Missile Transport
Bridge
Location: Vandenberg Air Force Base, CA
Owner: U. S. Army Corps of Engineers (Los
Angeles District)
Length: Approximately 2,100 L.F.
Contract Value at Award: $12,915,591
Completion Date: 12/01/03
|
|
The Missile Transport Bridge consisted
of the design and construction of a
2,098 lineal foot bridge on El Rancho
Road over San Antonio Creek. The bridge
includes 19 spans with 7-foot dia. CIDH
piles of up to 130 ft deep, pile caps,
piers, precast girders to support the
bridge deck, and 1,329 lf of approach
roadway. |
|
 |
| |
|
|
 |
|
The project design was completed under a
'Fast Track' design phase and accepted
on schedule, allowing construction
activities to begin on April 15 at the
start of the permitted construction
season. Vandenberg officials originally
estimated it would take two years to
complete the project. With an extremely
aggressive schedule and intensive
coordination with all members of the
project team, the work was actually
completed in 424 calendar days on
December 1, 2003, a full 306 days
early!. |
| |
|
|
|
|
 |
|